Prince Rupert Gas Transmission Project route map. (TransCanada website)

LNG pipeline for northwest B.C. still active

The 900km Prince Rupert Gas Transmission Project by TransCanada received approvals to expand

Despite the cancellation of the Pacific NorthWest LNG’s project on Lelu Island, the TransCanada Prince Rupert Gas Transmission Project is still alive.

The B.C. Environmental Assessment Office has approved of an amendment to alter the project description to increase its footprint by 53 hectares and increase the number of construction workers by 200 by adding two more work camps and eight additional compressor units.

The approval document is dated Dec. 20, 2017 for a pipeline project that was geared to service Petronas’ liquefied natural gas project before it was cancelled on July 25.

READ MORE: WCC LNG office to close in Rupert

Following Petronas’ announcement to end its project TransCanada stated on its website that it would review the options related to the proposed pipeline project “as we continue to focus on our significant investments in new and existing natural gas infrastructure to meet our customers’ needs.”

The specifics on how the pipeline will be used are still not known. Unfavourable market conditions ended Petronas’ ambition in Prince Rupert as well as other LNG projects in the area. Shell pulled its LNG project on Ridley Island in March, Nexen withdrew from its Digby Island LNG project in September and ExxonMobil-led WCC LNG closed its community office in December. But with this recent provincial amendment it is clear this project is still active.

READ MORE: Provincially approved LNG pipeline project faces legal hurdle

In the amendment document, the environmental assessment office stated they consulted with Lax Kw’alaams Band, Metlakatla First Nation, Gitanyow Hereditary Chiefs, Gitxsan Nation, Kitsumkalum First Nation, Nak’azdli Band, Takla Lake First Nation and Tl’azt’en Nation.

“Lax Kw’alaams Band and Metlakatla First Nation raised questions about the potential impact of the additional camps on local infrastructure and services,” the document states. However, the actual location of the camps are still unknown. TransCanana said it would aim to reduce impacts on local infrastructure.

The 780 kilometres of land based pipeline and 120 kilometres of marine based pipeline would end at Lelu Island, near Port Edward. The project received approvals in January 2017 from the B.C. government after the National Energy Board approved the northeastern pipeline with 45 conditions in April 2015.

READ MORE: Gitxaala sign LNG pipeline benefits agreement

 

shannon.lough@thenorthernview.com 

Like us on Facebook and follow us on Twitter 

Just Posted

New apartment building proposed in Tofino

Tim Hackett hopes to build a 32-unit, three-storey apartment building.

Tla-o-qui-aht First Nation demands transparency from leadership

“Right now there’s a lot of heartache.”

Tofino’s council split on ice rink decision

“I don’t think that’s the highest priority of the dollars that we have for a recreation facility.”

“Intense” storms coming to Tofino and Ucluelet this week

“If you are near the water, it is important to be ‘Coastsmart,’ by staying above the high tide.”

Ucluelet’s indoor market keeps vendors humming through the off-season

“It brings people out, which is great and we showcase different talents, which is great.”

WATCH: Giant waves smash Ucluelet’s Amphitrite Point

Folks made their way to Ucluelet’s Amphitrite Point Lighthouse on Thursday, Jan.… Continue reading

Christopher Garnier appealing murder conviction in death of off-duty cop

Jury found Garnier guilty in December, rejecting his claim she died accidentally during rough sex

Transportation watchdog must revisit air passenger obesity complaint

Canadian Transportation Agency must take new look at Gabor Lukacs’ complaint against Delta Air Lines

Gas plants verdict coming down today; ex-premier’s top aides to learn fate

Verdict to be delivered on senior staff to former Ontario premier Dalton McGuinty

WestJet appeals lost bid to scrap harassment lawsuit

Airline argues judge was wrong to have dismissed the company’s application to strike the legal action

Can U.S. border guards search your phone? Yes, and here’s how

Secretary of homeland security explains a new policy that let’s border guards check phones

‘Beautiful writer’ Nancy Richler dies of cancer in Vancouver hospital

Montreal-born author spent most of her adult life in B.C. as a fiction writer and novelist

Jury convicts spear-wielding Duncan man in 2015 Ladysmith RV park murder

Trever George Meers used a handmade spear to stab Rayna Johnson at the Campers Corners RV Park

Students frustrated by UBCO response to harassment allegations

Students on the Kelowna campus were unaware of resources and worried about lack of communication

Most Read